Home Mumbai Metro Line 4A (Green Line): Stations, Route Map, Status, & Timeline

Mumbai Metro Line 4A (Green Line): Stations, Route Map, Status, & Timeline

Mumbai Metro Line 4A – Green Line (Kasarvadavali – Gaimukh) metro corridor is 2.88 KM fully Elevated and consists 2 stations from Kasaravadavali – Gaimukh.

Metro corridor 4A is an extension of the Metro line 4 plan. Initially, Metro line 4 was planned to run the metro line between Wadala and Kasarvadavali. Later, the state government decided to extend the metro line until Gaimukh.

Indeed, the government had the plan to connect Gaimukh into a transport hub such that the commuters could easily connect to Thane, Mira-Bhayander, and Kalyan on the planned metro line stretch.

Moreover, demand from these areas is more, and presently commuters rely only on road connectivity. The official colour for the metro route stretch for metro lines 4, 4A, and 10 is Green and is called Mumbai Metro Green Line.

The Metro Line 4A is expected to bring additional ridership of about 1.5 lakh to 8.7 lakh commuters for the Wadala- Kasaravadavali Metro-4 corridor.

After successfully implementing the metro green line and red line, Residents from the Western suburbs, Thane, Kalyan, and other suburbs can reach their respective destinations without switching to different transportation modes.

Below is the list of stations on Mumbai Metro Line 4A i.e., Kasarvadavali – Gaimukh metro corridor. There are a total of 2 stations on the line, which are fully elevated.

#Station NameStatusTypeConnections
1KasarvadavaliUnder ConstructionElevatedInterconnect Mumbai Metro Line 4 – Green Line
2GowniwadaUnder ConstructionElevated

3GaimukhUnder ConstructionElevatedMumbai Metro Line 10 – Green Line

Mumbai Metro

Project/Metro Name: Kasaravadavali – Gaimukh Metro Corridor

Line Number: 4A

Official Line Color: Green

Status: Under Construction

Distance: 2.88 km

Total Stations: 2 Stations

Depot: Mogharpada (20 hectares)

Operator: Mumbai Metropolitan Region Development Authority (MMRDA)

Project Started: 2019

Project Completion: Expected to be completed by 2022

Estimated Cost: ₹949 Crore

Detailed Project Report (DPR)View Here

Website: https://mmrda.maharashtra.gov.in/metro-line-4#

Daily Estimated Ridership: 8.70 lakhs/day by 2021 and 12.13 lakhs/day by 2031. (Projection of Metro Line 4)

Metro Timings:

Metro Fare: –

Track length: 2.88km

Track Type: Elevated

Metro Type: Rapid Transit

Number of tracks: 2

Operating Speed: 80km/hr (50mph)

Track gauge: 1,435 mm (4 ft 8 1⁄2 in) standard gauge

Electrification: Overhead 25 kV AC