Home Mumbai Metro Line 7A (Red Line): Stations, Fare, Route Map, Status, & Timeline

Mumbai Metro Line 7A (Red Line): Stations, Fare, Route Map, Status, & Timeline

Mumbai Metro Line 7A (Andheri East – CSIA Terminal 2) metro corridor is 3.17KM Elevated (0.98 km) & Underground (2.915 km). The metro route consists of 2 stations from Andheri East – CSIA Terminal 2. 

Metro corridor 7A is an extension of the Metro 7 line plan. Initially, it was planned to run the metro line between Dahisar and Andheri, but later, the state government decided to extend the metro route. 

The official colour assigned to metro lines 7, 7A, and line 9 is Red which represents under Mumbai Metro Red Line.

Below is the list of stations on Mumbai Metro Line 7A i.e., Andheri East – CSIA Terminal 2 corridor. There are 2 stations on the line, which are Elevated (0.98 km) & Underground (2.915 km).

#Station NameStatusTypeConnections
1Andheri (East)Under ConstructionElevatedInterconnect Mumbai Metro Line 1 – Blue Line and Mumbai Metro Line 7 – Red Line
2Airport ColonyUnder ConstructionElevated
3CSIAUnder ConstructionUndergroundInterconnect Mumbai Metro Line 3 – Aqua Line

Mumbai Metro

Project/Metro Name: Andheri East – CSIA Terminal 2

Line Number: 7A

Official Line Color: Red

Status:Under Construction

Distance: 3.17KM

Total Stations: 2 Stations

Depot: Charkop(temporary), Bhayandar(Planned)

Operator: Mumbai Metropolitan Region Development Authority (MMRDA)

Project Started: March 2020

Project Completion: Expected to complete by December 2021

Estimated Cost: ₹ 6,518 crore (Metro Lines 7A & 9)

Detailed Project Report (DPR)View Here

Website: https://mmrda.maharashtra.gov.in/metro-line-9#

Daily Estimated Ridership: 8.47 lakhs/day by 2021 and 11.12 lakhs/day by 2031. (Estimation including Metro Line 9 and 7A)

Metro Timings:

Metro Fare: –

Track length: 3.17 km 

Track Type: Elevated (0.98 km) & Underground (2.915 km)

Metro Type: Rapid Transit

Number of tracks: 2

Operating Speed: 80km/hr (50mph)

Track gauge: 1,435 mm (4 ft 8 1⁄2 in) standard gauge

Electrification: Overhead 25 kV AC